MORLEY-IAS ZX Fire Alarm Control PanelsPage 14 Document No. 996-175-000-1, Revision 01 Commissioning Manual• Finally, select the INSPECT option from page 1 of the Commission Menus. Compare thecommissioning data entered against the installation sheets. This facility allows the data to beinspected without risking any inadvertent changes.4.5 Step 5 – Configure Day Mode Operation (If required)EN54!EN54-2 7.11Delays to Outputs• Select the DAY MODES option from Page 3 of theCommission Menus and then perform the following.1. Select ‘Delayed Mode’, if the sounders and outputs are to bedelayed. (NOTE: Must be enabled at Level 2 to activate).2. Select ‘Sensitivity Mode’, if the detectors are to have differentpre-alarm and fire alarm settings during day / night.3. Select ‘Verification Mode’, if the analogue signals are to beverified before the panel registers a fire alarm.• Program the required mode as required.4.6 Step 6 – Configure Network Options (If required)• Select the ‘NETWORK’ option from page 3 of the Commission Menus. Press ‘Yes’ to step througheach item to inspect the factory default settings and change as required. For example, panel address,number of slave panels, etc.4.7 Step 7 – Commence Normal Operation• Before finally commencing normal operation, perform the following.1. Select ‘PASSWORDS’ from page 2 of the Commission Menus. Set the number of Level 2 passwordsand define the value of each password.2. Select ‘PROGRAM INTEGRITY’ from page 2 of the Commission Menus. Check and record theprogram checksums.• Select ‘NORMAL OPERATION’ from page 1 of the Commission Menus.Remember to lock the memory!!!