GE Power Management SPM Synchronous Motor Protection & Control10-510 FUNCTIONAL TESTS 10.5 BRUSHLESS MOTOR FIELD APPLICATION TEST1010.5 BRUSHLESS MOTOR FIELD APPLICATION TEST 10.5.1 SETUP1. Connect the Va and Vb terminals of the 3-phase voltage source to SPM terminals B9 and B10 (controlpower and PF voltage reference) respectively. Program for 120 V AC.2. Connect the Switch to terminals A11 and A12 of the SPM (MX input). Close switch.3. Connect multimeters to TRIP and FCX relay outputs to monitor relay status.4. Connect a timer to start on MX switch opening and stop on FAR closure to check timing. Repeat with FARand FCX respectively for FCX timing.10.5.2 RELAY PROGRAMMINGa) CONFIGURATIONSProgram as defaults shown in Section 5.4: CONFIGURATIONS MENU on page 5–12.b) SETPOINTSProgram as defaults shown in 5.2: SETPOINTS MENU on page 5–2.10.5.3 TEST1. Apply control power to relay and wait for self-test diagnostic to complete. Should get SPM READY mes-sage and TRIP relay should close.2. Open MX switch3. FAR contact should close after FAR DELAY expires followed by FCX contact. FIELD IS APPLIED mes-sage should momentarily flash on screen.Table 10–4: BRUSHLESS MOTOR FIELD APPLICATION TEST RESULTSSETPOINTS RESULTSFAR DELAY FCX DELAY FAR OPERATION FCX OPERATION0 110 560 10