Commissioning8.11 Information pertaining to component replacementsSafety Integrated238 Function Manual, 05/2010, A5E03264275A5. Carry out a POWER ON (power off/on) for all components.NoteIn this case, the system will not notify you with a flashing LED that a POWER ON isrequired.6. Carry out an acceptance text and acceptance report according to Chapter "Acceptancetest and acceptance report" and table "Effect of the acceptance test for certainmeasures".WARNINGBefore re-entering the danger area and before resuming operation, a (partial) acceptancetest must be carried out for all the drives affected by the component exchange (see the"Acceptance test and acceptance report" chapter).