Installing the Switch ChassisThis chapter includes the following topics:• Installing a Rack or Cabinet, on page 1• Unpacking and Inspecting a New Switch, on page 2• Installing the Chassis in a Two-Post Rack, on page 3• Installing the Chassis on a Four-Post Rack or Cabinet, on page 7• Grounding a Switch Chassis, on page 10• Installing Cable Management Frames onto the Chassis , on page 11• Attaching the Front Door to the Chassis, on page 13Installing a Rack or CabinetBefore you install the switch, you must install a standard four-post, 19-inch EIA data center rack (or a cabinetthat contains such a rack) Cabinet and Rack Requirements.Step 1 Bolt the rack to the concrete subfloor before moving the chassis onto it.Stability hazard. The rack stabilizing mechanism must be in place, or the rack must be bolted to the floor beforeyou slide the unit out for servicing. Failure to stabilize the rack can cause the rack to tip over.NoteStep 2 If the rack has bonded construction, connect it to the earth ground. This action enables you to easily ground the switchand its components and to ground your electrostatic discharge (ESD) wrist strap to prevent damaging discharges whenyou handle ungrounded components before installing them.Step 3 If you need access to the source power at the rack, include either AC power receptacles or a DC power interface unit(PIU) with the amperage required by the switch that you are installing. .If you are using DC power, be sure that the DC power supply is grounded and that there is direct access to the facilityDC power or indirect access though a power interface unit (PIU). You must connect the DC power supply to the earthground before you connect it to the facility DC power.Take care when connecting units to the supply circuit so that wiring is not overloaded.NoteInstalling the Switch Chassis1