4‐16 Operation MN2408When the controller is applied in an Auto Mains Failure (AMF) application with a transfer switch,it must be wired as shown in Figure 4‐14. Programmable output #3 must be selected for UtilityReady To Load and programmable output #4 must be selected for Gen Ready To Load. After thecontroller is programmed, the AMF sequence of operation will be as follows:Utility Normal Condition:1. Remote Start input signal (terminals 16 & 17) is not activated (i.e. normal).2. Utility Ready To Load output is energized (i.e. signal to transfer switch to transfer toutility power).3. Generator Ready To Load output is de-energized.Utility Power Failure Conditions:1. Remote Start input signal is activated (i.e. remote start contact closes when utilitypower fails, as sensed by utility voltage sensor).2. Engine starts after the Engine Start Delay timer (Utility Ready To Load output staysenergized).3. After the engine has started and the generator output rises above the programmedvoltage and frequency limits, a Warm-Up timer is initiated.4. After the Warm-Up timer expires the Utility Ready to Load output de-energizes and theNEUTRAL Delay timer is initiated.5. After the NEUTRAL DELAY timer expires the Gen Ready to Load output energizes tosignal the transfer switch to transfer to the generator supply. Note: The neutral delayfunction is only operative with an electrically-held type transfer switch mechanism(ie. electrical contactor type).Utility Power Restored:1. Remote Start input signal is removed and the Return Delay timer is initiated (i.e. UtilityVoltage returns to normal and the Utility voltage sensor contact opens).2. After the Return Delay timer expires, the Generator Ready to Load outputde-energizes and the Neutral Delay timer is initiated.3. After the Neutral Delay timer expires the Utility Ready to Load output energizes tosignal the transfer switch to transfer to the utility supply. Note: If the generator has ashutdown during the Return or Neutral Delay periods, the timers are bypassed, and theUtility Ready to Load output immediately energizes.4. The generator Cool down Timer starts after the Return Delay timer.5. The generator stops after the Cool down Timer.Load Test Push-button Operation1. When the Load Test pushbutton is pressed, the logic will internally simulate receiving aremote start input.2. Engine starts after the Engine Start delay timer.3. After the engine has started and the generator output rises above the programmedvoltage and frequency limits, a Warm-Up timer is initiated.4. After the Warm-Up timer expires the Utility Ready to Load output de-energizes and theNeutral Delay timer is initiated.5. After the Neutral Timer expires the Gen Ready To Load output energizes to signal thetransfer switch to transfer to the generator supply.Note: If a generator shutdown occurs during a Load Test Operation, the Load Test mode will bede-activated.When Auto Mode is restored (after Load Test Operation) the following occurs:1. Simulated Remote Start input signal is removed.2. Gen Ready To Load output de-energizes, and Neutral Delay timer is initiated.3. After the Neutral Delay timer expires The Utility Ready To Load output energizes tosignal the transfer switch to transfer to the utility supply.4. The generator Cool down timer starts timing following the transfer to the utility supply.5. The generator stops after the Cool down timer.